by Sue McFadden | Aug 18, 2017 | Lisgar Flooding
Current Activities The draft report related to the storm sewer leakage testing in the Golden Locust Drive area has been received and is currently being reviewed by staff; Flushing of the FDC system is on-going and is approximately 50% complete. Operations staff noted...
by Sue McFadden | Aug 18, 2017 | Lisgar Flooding
In early August, I scheduled a face-to-face meeting with Mickey Frost, Director of Works and Operations, and Helen Noehammer, Director of Transportation and Infrastructure Planning, to bring forward some of my concerns and those of affected residents regarding the...
by Sue McFadden | Aug 11, 2017 | Lisgar Flooding
Current Activities The leakage testing of the Phase 1 storm sewer lining (in the Golden Locust Drive area) has been completed and AmecFW has advised that we will receive the testing report early next week. The draft memo summarizing the monitoring results of the July...
by Sue McFadden | Aug 7, 2017 | Lisgar Flooding
Current Activities The leakage testing of the Phase 1 storm sewer lining (in the Golden Locust Drive area) was completed on Wednesday, July 26th. We are anticipating receiving the testing report by the end of next week. The draft memo summarizing the monitoring...